City of Jackson Construction Update July 22, 2022
(July 22, 2022 8:56 PM) The City of Jackson has released the weekly construction update for the following projects: West Avenue construction update: Over the past week, the excavation crew has worked to install new storm water catch basins and associated sewer pipe within the intersection of West and Franklin. This work is now approximately 30% complete. This work will be completed next week and then the site will be graded in preparation for the arrival of the concrete subcontractor. Earlier today, the electricians began their work to replace the traffic signal at the West and Franklin intersection. They are currently installing conduits and handholes around the intersection so that the underground work can be completed before the new curbs and sidewalks are built. The concrete subcontractor is scheduled to arrive in the first week of August to build the new curbs, driveways and sidewalks for the realigned intersection at West and Franklin. E. High Street bridge construction update: Over the past week, the contractor continued preparations for the pouring of the new bridge deck by putting reinforcement steel and temporary wood forms into place. This work will continue until concrete for the new deck is poured in the first…