The I-94 Elm Road interchange last fall. MDOT photo.
(March 10, 2023 3:10 PM) The Michigan Department of Transportation (MDOT) will shift westbound I-94 between M-106 (Cooper Street) and US-127 Monday. The exit ramp from westbound I-94 to Elm Road will be closed for rebuilding.
This work is part of MDOT’s ongoing $120 million investment to rebuild and widen I-94 near the Airport Road interchange to just west of the east US-127/I-94 interchange in Blackman and Leoni Township. The I-94 project involves upgrading the US-127/M-50 (West Avenue)/I-94 interchange to a diverging diamond interchange, the Elm Road interchange with roundabouts, and the Lansing Avenue bridge over I-94.
Start date:
7 a.m.
Monday, March 13, 2023
Completion date:
3 p.m.
Friday, June 30, 2023
Overall I-94 project completion date:
November 2023
Traffic restrictions:
This project will require a single-lane closure on westbound I-94 while the traffic shift is in process.
Westbound I-94 to Elm Road traffic will be detoured west via I-94 to M-106 (Cooper Street), north to Parnall Road, and east to Elm Road.
Motorists are advised to seek alternate routes.